If you plan to serve AI inference from Las Vegas, test what happens when the remaining replicas must handle the same stream of requests. A deployment can stay online and still fail its users: the endpoint accepts connections, but people wait long enough to see timeouts or unfinished answers. A useful failover test measures the responses users receive, not just whether a dashboard shows a healthy service.

Start after you've selected the site or the service. The Las Vegas colocation buyer's guide covers the earlier decision: what to ask about power, network handoffs and the service-ready date. A strong answer to those questions still won't tell you whether your particular model can take over a full queue when a serving replica goes away.

Define which failure the test actually covers

For a first exercise, remove one inference replica in an approved test environment. Keep the same model version and request mix. Do not change a production load balancer or disconnect facility equipment to prove this case. If you are buying managed inference and cannot control a replica, ask the provider to run the exercise in its test environment while your team measures the client side.

The result applies to the failure you rehearsed. One lost replica is not proof that you can lose an entire rack, a building, a regional endpoint or a shared retrieval service. Where your fallback changes the model, deployment region or data path, record that as a different exercise with its own acceptance criteria.

Agree on the following before the test:

  • Which client locations and connection paths represent the people using the application.
  • Which request sizes, concurrency patterns, output caps and timeouts represent the service you plan to offer.
  • Which successes count. A stream that emits a token and then stops is not a complete answer.
  • What the system should do when it cannot keep up. If it rejects work, queues it, or switches to a smaller model, say which responses are acceptable and who approved the trade-off.

Measure the client response and the server queue separately

Start the client clock before the request leaves the client, and stop it at the first usable output token. Track full completion independently. That first-token number can include connection time and application dependencies as well as model serving, so do not describe a server-side metric as the same measurement.

On the server, watch how many requests are waiting and how long requests spend in the scheduler queue. vLLM's production metrics documentation lists queue-time, first-token and end-to-end latency histograms, along with gauges for running and waiting requests. Confirm that your installed version and configuration expose the relevant metrics. If you use another serving engine, look for measurements with equivalent boundaries, not just similar names.

Read the two sides together. If client first-token time and server queue time rise together, the serving queue is a reasonable place to look. If the client slows down while server timings hold steady, check the gateway, the network path and dependencies such as retrieval. Neither pattern alone proves a cause. Don't subtract two p95 values to estimate network latency or add percentiles from different stages to estimate total latency.

Measure What to capture What it helps you decide
Original requests offered Count each logical request once, separate from retry attempts Whether the compared runs received the same load
Time to first usable token Client p95 for the defined cohort, with sample count and the number with no first token Whether the start of a streamed response feels slower
Completed, timed out, failed Mutually exclusive outcomes for original requests; call out incomplete streams Whether apparently fast responses conceal failures
Scheduler queue Queue time and waiting requests during the same measurement windows Whether spare serving capacity is absorbing the load
Recovery Time to return within the agreed bounds and stay there for a chosen window When the application can be considered recovered

Run the test in three windows

Baseline. Use synthetic requests without customer prompts or secrets. Record the tested model and deployment, prompt length mix, output cap, request rate and timeout. Note the cache state. If the production application depends on warmed caches, include a separate cold-start test instead of calling a fully warmed run representative of both conditions.

One replica unavailable. Remove only the agreed replica in the test environment. Keep the load coming on the same schedule rather than slowing the driver to wait for each response. Observe what happens to requests already in flight, to new requests, and to client retries. If retries are permitted, keep their budget fixed and count the extra attempts so you can see whether they make the queue worse.

Recovery. Return to the intended configuration and leave the request pattern unchanged. Record when the queue starts draining and when the client-facing service clears its thresholds. Watch for a second increase as traffic moves back or a cold replica catches up. A short healthy sample is not evidence that a growing queue is gone.

An example of what can hide behind a fast p95

Suppose a controlled run offers 1,000 original requests after one replica goes offline. Of those, 950 complete, 30 time out and 20 fail another way. Completion is 95%. If the first-token chart includes only the requests that produced a token, the chart can still look good while 50 requests fail to deliver a complete response.

Compare that run with the baseline at the same offered load. If your tool shows a larger number of attempts because some logical requests retried, don't use the larger number to make completion look better. Keep the 1,000 original requests as the denominator and report the attempt count separately.

These figures are hypothetical. They aren't a Las Vegas measurement, a vendor result or suggested performance targets.

Bring the result back to the deployment decision

Record the pass criteria in your rollout plan before anyone looks at results. It should name the client test population and the accepted limits for first-token latency, completion, and recovery under the failure you chose. Include the conditions tested, the model version and a link to the measurement record. If the fallback uses less capacity or serves a different model, a performance pass does not settle output quality or data-handling questions.

For a Las Vegas deployment, ask the operator which capacity goes with your specific order. Check whether the fallback replica shares a host, rack or facility dependency that matters for the next test. Keep facility recovery obligations in the colocation contract and application recovery obligations in the rollout plan. Neither document answers both questions by itself.

Questions before you sign off on GPU failover

Does a passing health check mean the replica can take more load?

No. A health check can show an endpoint is responsive without telling you how much work it can complete at your target load. Measure the application response under the failure condition you intend to tolerate.

Should first-token latency include timed-out requests?

Report what the latency sample includes. A request with no first token cannot contribute a measured first-token latency. Count it separately in the same window, so it doesn't disappear from the result. Report full completion as a separate measure.

Is it safe to use production prompts in the test?

Use synthetic prompts that reflect the size and shape of the work. Keep identifying or confidential material out of the test, its provider tooling, and the logs.

Can the test compare Las Vegas with another serving region?

Yes, if the client origin, model, request mix and measurement boundaries match. If the fallback changes the model, architecture, or data destination, describe what changed instead of attributing the full difference to geography.

How long should the recovery observation run?

Pick a window that is long enough for your system to drain the queues created during the exercise and settle at the intended request rate. Agree on that window before the run. Don't stop the clock the moment one successful response appears.

What should a managed provider hand back?

Ask for the exact test conditions, the offered load, the breakdown of request outcomes, and the start and stop times for the exercise. Compare those records with your client observations. A screenshot of provider uptime alone is not an inference failover result.

For the next deployment review, take one sentence you can verify: With one serving replica unavailable, this model must finish this request mix under these bounds. That is a condition your team can test, document and revisit when the deployment changes.

Make the test scope clear to buyers

If you market an inference service, explain what changed in the test and what was held constant. Give buyers the model, load and failure conditions next to the result. Percepture's data center marketing guide covers how to present technical evidence without turning it into an unsupported promise.

Bob Generale, President of Percepture